The release planning event in the Scaled Agile Framework Enterprise (SAFe) is a two-day program-level planning event that focuses the efforts of a group of teams to pursue a common vision and mission. As we have noted, the event includes participation by everyone involved in the Agile release train (ART), participation is in-person (if humanly possible), occurs every 8 – 12 weeks and has a formal structured agenda.   The agenda has five major components:

  1. Synchronization.  This component seeks to get everyone involved in the ART on the same page in terms of:
    1. Business Context
    2. Product Vision
    3. Architectural Vision
    4. Technical Environment and Standards

Each of these subcomponents provide the team with an understanding of what they are being asked to do and the environment they are being asked to operate within. The flow begins by grounding the team the business context for the program increment (the 8 -12 weeks). Each step after the business context increased in technical detail.

  1. Draft Planning. Leveraging the context, vision, architecture and environmental standards, the teams develop a draft plan. We will explore the process in greater detail in a later essay, however this where the team breakdown the stories they will tackle during the program increment, breaks them down, exposes risks and identifies and minimizes dependencies.   Draft planning usually consumes the second half of the day. The Release Train Engineer will gather the scrum masters together periodically during the draft planning process to ensure teams are sharing dependencies and understand the direction each is heading.
  2. Management Review and Problem Solving. At the end of draft planning, any significant problems with the scope of the program increment, staffing or other resource constraints are generally apparent. After the majority of team has completed their work for the day the management team (including RTE and scrum masters) meets to share what was learned and make the decisions needed to adjust to the constraints. This is must be completed before the beginning of day two.
  3. Final Planning. The teams review the adjustments made during the during the management review the previous evening as a whole group and then break out into teams again to continue planning converting the draft plans into final(ish) plans. Plans are finalized when they are accepted by the business owners.
  4. Review, Re-planning and Acceptance. When the teams plans are finalized they are reviewed by the whole team, the risks are ROAMed, the whole team votes on acceptance (a form of peer review and acceptance), any rework is performed on the plan and finally a retrospective is performed and next steps identified.

The release planning meeting operationalizes a program increment. A program increment represents 8 – 12 week planning horizon within a larger Agile Release Train. The large scale planning event helps keep all of the teams involved in the ART synchronized. The release planning meeting might be SAFe’s special sauce.